|
|
||
Buffer
Buffer
1) ‘Enough’ what?
1) Time. The unit of measurement for a buffer is time. In a production environment it is the amount of time we use to release material ‘early’ to make the constraint work. In Project Management it is the amount of time we accumulate at the end of the project before the set delivery date. 2) We consider a buffer to be made up of three zones, zone one being the one nearest the constraint. What we now have to ask ourselves is: how much of this buffer can we use up in total safety? Only the external part, zone three. If we get into zone two we have to ask what’s happening and why what we were expecting hasn’t arrived. If we get into zone one, we have to take immediate action to get things moving. No ifs and buts, we must have things now. Otherwise we lose throughput. The length of the buffer is determined by the predictability, or interval of variation of the in-control processes that impact the constraint. The higher the variation, the longer the buffer time has to be. A perfectly in-control process could do without zone three. In the same way, in a completely out-of-control process, zone three would be equivalent to zone one. So what should we do? It is essential to remember that we cannot predict the outcome of any managerial action if it is not taken in an environment made up of stable and in-control processes. Consequently, if we want to get the most from buffer management we have to make sure that: - all the major processes
that impact the constraint are stable
We know that the
processes in our system are, by definition, affected by variation.
As these processes are strongly interconnected, this variation inevitably
influences the constraint’s performance and therefore the Throughput
of the whole system.
In this way, we reduce daily pressure and stress and we gain time to analyze and understand the causes that block the production flow. This analysis generates a positive feedback loop which strengthens the solution and creates an opportunity for further improvement. Buffer Management: Production In a manufacturing industry, the buffer controller visits the Finished Goods area and checks the number of products ready for shipping. Every unit under the scheduled number is considered missing and constitutes a ‘hole’ in the buffer. The way we react to a hole in the buffer depends on the time left before the delivery date. In zone three we are likely to find holes in the buffer, due to the transfer time from the Raw Materials area to the Finished Goods area. In zone two we expect
to see some units arrive in the Finished Goods area. The only reason for
a unit to be missing in this area is because it’s been held up due to an
interruption in the production flow.
In zone one, we take
immediate action to remedy the situation and guarantee on-time shipping.
The normal trend
for the arrival of units in the Finished Goods area can be illustrated
by the following graph
Thanks to the increased
focus gained through Buffer Management, and the preventive actions
it allows us to take, we can expect the graph to change to the following
Buffer Management: Project Management What is the constraint in Project Management? The Critical Chain Exploiting (see
Five Focusing Steps) the Critical Chain means doing everything necessary
to guarantee that tasks are not late according to the schedule, including
detailed planning; protecting the duration of the entire project and not
just the duration of single activities.
To protect ourselves
from scarcity of resources and guarantee that the resources we have allocated
along the Critical Chain are there when we need them, we use the resource
buffer.
Subordinating
(see Five Focusing Steps) the rest of the scheduling to the Critical
Chain means making sure that all the other resources do whatever possible
to guarantee that the task scheduling is respected.
The way to get out
of this conflict is to shift the beginning of activities as far ahead as
possible while guaranteeing that the project will not finish late.
|
|
||
|
|||